Net Metering Application Guide
Generate your own electricity and earn credits for excess energy delivered back to the grid. Follow the steps below to apply.
| Step |
Stage |
Action Required |
Timeline |
| I |
Submit Requirements |
Email all documents to ZAMECO II |
Upon application |
| II |
Inspection & Clearances |
Account clearance, initial and final inspection |
2–4 working days |
| III |
ERC Payment |
Pay ₱1,500 Certificate of Compliance fee |
Upon billing |
| IV |
Meter Installation |
Installation of Bi-Directional Meter |
5 working days |
I
Requirements
Primary Requirements
| # |
Document |
Details |
| 1 |
Letter of Intent |
Intent to engage in net metering program |
| 2 |
Copy of Government-Issued ID |
Driver’s License, Passport, GSIS, etc. |
| 3 |
Single Line Diagram |
Solar PV system — signed and sealed by PEE |
| 4 |
Certificate of Completion |
Annex 2 – JMC 001, S26 — from Building Official (Municipality) |
| 5 |
ZAMECO II Statement of Account |
Latest electric bill (Resibo ng kuryente) |
| 6 |
ERC Certificate of Compliance |
Accomplished COC form for Qualified End-User |
| 7 |
Google Map of Location |
GPS coordinates and Google Maps link of the installation site |
| 8 |
Facility Photos |
Meter Base, Disconnect Switch, and other facility components |
| 9 |
Letter of Authorization |
Use the official template attached to the application package Download Application Guide |
Additional Requirements If Applicable
| Authorization Letter + Valid ID |
Required when a representative is filing on behalf of the applicant |
| Notarized Special Power of Attorney |
Photocopy and original |
| Deceased Account Holder |
Account name must be transferred/changed first before application |
| Contract of Lease / Commercial |
Required for leased or commercial properties |
II
Inspection & Clearances
| Stage |
Description |
Timeline |
| 🔍 Account Clearance |
Verification that the consumer account is in good standing — bills paid before due date. Certification of Billing required. |
Upon submission |
| ⚡ Initial Inspection |
Initial inspection of solar photovoltaic system and metering facility to
be provided by the consumer. (2 to 4 days upon receipt of complete documents.)
|
2–4 working days |
| ✅ Final Inspection |
Final inspection to confirm compliance with standard metering facility requirements. Consumer must notify the office via call or text to schedule. |
Upon consumer notice |
III
Payment for ERC Certificate of Compliance
| Item |
Details |
Amount |
| ERC Application Fee |
Collected by ZAMECO II on behalf of the Energy Regulatory Commission (ERC). An Acknowledgement Receipt will be issued. |
₱1,500.00 |
| Official Receipt (ERC) |
ZAMECO II will furnish the consumer with a copy of the Official Receipt from ERC via email. |
— |
IV
Installation of Bi-Directional Meter
| Activity |
Condition |
Timeline |
| 🔌 Bi-Directional Meter Installation |
Upon completion of the net metering facility and fulfillment of all preceding requirements. |
Within 5 working days |
Download Application Guide