π Notice of National Grid Corporation of the Philippines Scheduled Power Interruption
π Published: June 17, 2025
π Date | β° Time/Duration |
June 21, 2025 (Saturday) |
5:30 AM to 6:00 AM |
π Affected Areas | |
β’ Whole area of Subic (including Alta Vista and P13 Baloy) β’ Whole area of Castillejos β’ Whole area of San Marcelino β’ Whole area of San Antonio β’ Whole area of San Narciso β’ Whole area of San Felipe β’ Whole area of Cabangan |
|
π οΈ Purpose | |
Shutdown of the 100MVA Transformer 1 at Olongapo SS to facilitate the replacement of circuit breaker pole column 8B-CB04 (8Z-XF01OLO) due to the detection of critical corona discharge |
π Published: June 17, 2025
π Date | β° Time/Duration |
June 23, 2025 (Monday) |
12:00 AM to 12:30 AM |
π Affected Areas | |
β’ Whole area of Subic (including Alta Vista and P13 Baloy) β’ Whole area of Castillejos β’ Whole area of San Marcelino β’ Whole area of San Antonio β’ Whole area of San Narciso β’ Whole area of San Felipe β’ Whole area of Cabangan |
|
π οΈ Purpose | |
Shifting of Olongapo-Cawag 69kV line load to Botolan-Castillejos 69kV line and vice versa |