EMERGENCY POWER INTERRUPTION ADVISORY
June 4, 2025
Date | TIME DURATION | AFFECTED AREAS | PURPOSE | |
From | To | |||
4-Jun-25 | 9:00 AM | 5:00 PM | > Parts of Grullo at San Narciso | > To facilitate relocation of pole and rerouting of primary lines Clearing of critical vegetation |
We hope the consumers affected and the public in general will be guided by this announcement by this announcement
NOTICE OF SCHEDULED POWER INTERRUPTION
June 5, 2025
Date | TIME DURATION | AFFECTED AREAS | PURPOSE | |
From | To | |||
5-Jun-25 (Thursday) |
9:00 AM | 4:00 PM | > Whole area of Coastal Road San Felipe | > To facilitate installation of new primary pole and distribution transformer >Clearing of critical vegetation |
NOTICE OF NGCP SCHEDULED POWER INTERRUPTION
June 11, 2025
NOTICE OF NATIONAL GRID CORPORATION OF THE PHILIPPINES (NGCP) SCHEDULED POWER INTERRUPTION
ZAMECO II – Calapacuan, RGS Ice Plant, Castillejos, SanMarcelino,
NETDC San Antonio, San Narciso, San Felipe S/S
ZAMECO I – Taugtog S/S
Consort Land Inc.
Dear Valued Customers:
Please be Informed that we are scheduling power service interruption to your area/power system, details are as follows.
Date/Day Time |
Line/Equipment to be De-energized |
Activities |
June 11, 2025
Wednesday 0530H-0630H Affected loads: · ZAMECO II -Calapacuan, RGS Ice Plant, Castillejos, San Marcelino, NETDC San Antonio, San Narciso, San Felipe · ZAMECO I – Taugtog · Consort Land Inc. |
Botolan-Castillejos 69 kV Line and Olongapo Cawag 69 kV Lfne |
Momentary outage for shifting and isolation of loads. Replacement of insulators at the isolated segment. Isolation of NETDC San Antonio Line Segment. · Consort Land Inc. and RGS Ice Plant connected to Botolan S/S · Calapacuan S/S connected to Olongapo S/S |
June 11, 2025
Wednesday 1800H-1900H Affected loads: · ZAMECO II – Calapacuan, RGS Ice Plant, Castillejos, San Marcelino, NETDC San Antonio, San Narciso, San Felipe · ZAMECO I – Taugtog · Consort Land Inc. |
Botolan-Castillejos 69 kV Line and Olongapo-Cawag 69 kV Line |
Momentary outage for shifting and isolation of loads (Normalization).
· Taugtog S/S connected to Botolan S/S · San Felipe S/S connected to Olongapo S/S · NETDC San Antonio line segment isolated |
“In case you or your customers will operate standby generator set during the shutdown, please make sure to trip-off/open your respective breaker/isolator going to our line to ensure safety of our maintenance personnel.”