November 30, 2024
| Date | TIME DURATION | AFFECTED AREAS | PURPOSE | |
| From | To | |||
| November 30, 2024
(Saturday) |
8:30 AM | 09:00 AM | > Whole Area of Magsaysay (except Govic Rd)
> Whole Area of Sta Maria (except Sibol) > Whole Area of San Agustin (except Sibul, Old San Agustin and Madamguiz) > Whole Area of San Jose (except street from Jireh Home to day care and Uguit) > Whole Area of San Juan > Whole Area of San Nicolas > Whole Area of Balaybay > Whole Area of Del Pilar (except Caballucan) > Whole Area of San Roque (except Govic Rd) > Whole Area of San Pablo (except San Isidro, Kanaynayan, Bagong Silang and near Govic Rd) > Part of Pamatawan (riverside) (1 DT only)
|
> Momentary shutdown to facilitate isolation of line.
|
| 8:30 AM | 4:00 PM | > Part of San Juan Castillejos | > To facilitate relocation of primary pole of Castillejos Municipal Hall.
|
|

November 26, 2024
| Date | TIME DURATION | AFFECTED AREAS | PURPOSE | |
| From | To | |||
| November 26, 2024
(Tuesday) |
8:00 AM | 09:00 AM | > Whole Area of Calapandayan, Ilwas, Baraca Camachile, Asinan Poblacion, Wawandue (except Bridge)
> Parts of Asinan Proper (Brgy Hall), Parts of Manganvaca (P1, near SNHS and beside Waltermart)
|
>Isolation of Line and Load Shifting |
| 8:30 AM | 9:00 AM | > Parts of Cawag of Subic (Club, Morroco, Cawag Proper, Resettlement, St. Martin, Agusuhin, Nagyantok going to Hanjin areas), Parts of Wawandue of Subic
|
> Isolation of Line and Load Shifting | |
| 8:00 AM | 6:00 PM | > Parts of Calapacuan (Sta Elena to Subic Beach Nat’l Hiway, Sta Elena to Nat’l Hiway near JLM Hardware
> Parts of Baraca Camachile (Pandayan Bldg to New Public market)
|
> Rehabilitation of three phase primary line
> To facilitate rerouting of primary line per DPWH |
|
| 5:00 PM | 5:30 PM | > Parts of Cawag of Subic (Club, Morroco, Cawag Proper, Resettlement, St. Martin, Agusuhin, Nagyantok going to Hanjin areas)
> Whole Area of Calapandayan, Ilwas, Baraca Camachile, Asinan Poblacion, Wawandue > Parts of Manganvaca (P1, near SNHS and beside Waltermart) > Parts of Asinan Proper (Brgy Hall) |
Normalization of Loads
|
|
| 5:00 PM | 06:00 PM | Parts of Calapacuan | Normalization of Loads
|
|
Notice of Power Service Interruption November 27, 2024
| Date | TIME DURATION | AFFECTED AREAS | PURPOSE | |
| From | To | |||
| November 27, 2024
(Wednesday) |
8:00 AM | 9:00 AM | > Part of Linasin (near Substation)
> Whole Area of San Isidro > Parts of Consuelo Sur (along Hi-way) > Whole Area of San Guillermo > Whole Area of La Paz > Parts of Nagbunga, San Marcelino (WLAC Road)
> Parts of Nagbunga, Castillejos
|
> Momentary shutdown to facilitate load shifting.
|
| 8:00 AM | 06:00 PM | > Whole of Sto Domingo
> Whole Area of Linusungan > Whole Area of Angeles > Whole Area of San Esteban > Parts of Buenavista (Boundary to Linusungan) > Part of Nagbunga, San Marcelino
|
> To facilitate paralleling of three phase line.
> To facilitate removal of old pole in front of SAVEMORE San Marcelino. > To facilitate replacement of rotten primary poles at Angeles.
|
|
| 05:00 PM | 06:00 PM | > Part of Linasin (near Substation)
> Whole Area of San Isidro > Parts of Consuelo Sur (along Hi-way) > Whole Area of San Guillermo > Whole Area of La Paz > Parts of Nagbunga, San Marcelino (WLAC Road)
> Parts of Nagbunga, Castillejos
|
> Normalization of loads. | |