Power Interruption

NOTICE OF SCHEDULED POWER INTERRUPTION

? Notice of Scheduled Power Interruption

? Published: June 26, 2025

? Date ⏰ Time/Duration
June 28, 2025
(Saturday)
8:30 AM to 4:00 PM
? Affected Areas
• Major parts of San Juan, Castillejos
?️ Purpose
Clearing of Critical Vegetation along Power Distribution Line as requested by LGU Castillejos

NOTICE OF SCHEDULED POWER INTERRUPTION

? Notice of Scheduled Power Interruption

? Published: June 17, 2025

? Date ⏰ Time/Duration
June 19, 2025
(Thursday)
8:30 AM to 4:00 PM
? Affected Areas
• Major Parts of Baloy of Barretto
(from street going to beach, including beachside area)
?️ Purpose
Clearing of Critical Vegetation along Power Distribution Line

NATIONAL GRID CORPORATION OF THE PHILIPPINE SCHEDULE POWER INTERRUPTION

? Notice of National Grid Corporation of the Philippines Scheduled Power Interruption

? Published: June 17, 2025

? Date ⏰ Time/Duration
June 21, 2025
(Saturday)
5:30 AM to 6:00 AM
? Affected Areas
• Whole area of Subic (including Alta Vista and P13 Baloy)
• Whole area of Castillejos
• Whole area of San Marcelino
• Whole area of San Antonio
• Whole area of San Narciso
• Whole area of San Felipe
• Whole area of Cabangan
?️ Purpose
Shutdown of the 100MVA Transformer 1 at Olongapo SS to facilitate the
replacement of circuit breaker pole column 8B-CB04 (8Z-XF01OLO) due
to the detection of critical corona discharge

 

? Published: June 17, 2025

? Date ⏰ Time/Duration
June 23, 2025
(Monday)
12:00 AM to 12:30 AM
? Affected Areas
• Whole area of Subic (including Alta Vista and P13 Baloy)
• Whole area of Castillejos
• Whole area of San Marcelino
• Whole area of San Antonio
• Whole area of San Narciso
• Whole area of San Felipe
• Whole area of Cabangan
?️ Purpose
Shifting of Olongapo-Cawag 69kV line load to Botolan-Castillejos 69kV line and vice versa

 

 