January 16, 2025 (CANCELLED)
| Date | TIME DURATION | AFFECTED AREAS | PURPOSE | |
| From | To | |||
| January 16, 2025 (Thursday) |
8:30 AM
|
5:30 PM
|
> Part of Calapacuan Subic Natl Hi-way (Maligaya Village to Studio 23)
|
> To facilitate replacement of Primary line near Subic Beach.
|
| 8:30 AM
4:30 PM |
9:00 AM
5:30 PM |
> Part of Calapacuan
> Whole of Calapandayan > Whole of Ilwas > Whole of Baraca Camachile > Whole of Wawandue > Whole of Asinan Poblacion > Whole of Manganvaca > Whole of Asinan Proper > Whole of Cawag > Whole of Pamatawan > Whole of Aningway Sacatihan
|
> Momentary shutdown to facilitate load shifting and normalization. | |
| 8:30 AM
4:30 PM |
9:00 AM
5:30 PM |
>Part of San Roque and San Nicolas, Castillejos
>Whole area of Del Pilar, Castillejos |
> Momentary shutdown to facilitate load shifting and normalization. | |
January 15, 2025 (CANCELLED)
| Date | TIME DURATION | AFFECTED AREAS | PURPOSE | ||
| From | To | ||||
| January 15, 2025 (Wednesday) |
8:00 AM | 5:30 PM | > Parts of Nagbunga Castillejos
> Whole of Buenavista Castillejos (except boundary to Linusungan) > Whole of Balaybay Castillejos
|
> To facilitate replacement of Primary line, relocation of pole and balancing of loads. | |
| 8:00 AM
|
12:00 PM
|
> Whole of Magsaysay
> Whole of Sta Maria > Whole of San Agustin > Whole of San Jose > Whole of San Juan > Whole of San Nicolas > Whole of Del Pilar > Whole of San Roque > Whole of San Pablo > Part of Pamatawan (riverside 1DT only) > Whole of Looc > Whole of Nagbayan > Parts of Nagbunga |
> Momentary shutdown to facilitate load shifting and normalization. | ||
| 05:00 PM | 5:30 PM | > Whole of Magsaysay (except Govic Road)
> Whole of Sta Maria (except Sibul) > Whole of San Agustin (except Sibul, Old San Agustin and Madamguiz) > Whole of San Jose (except street from Jireh Home to day care and Uguit) > Whole of San Juan > Whole of San Nicolas > Whole of Del Pilar (except Caballucan) > Whole of San Roque (except Govic Rd) > Whole of San Pablo (except San isidro, Kanaynayan, Bagong Silang and near Govic Road > Part of Pamatawn (riverside 1DT only)
|
> Momentary shutdown to facilitate normalization. | ||
January 14, 2024 (CANCELLED)
| Date | TIME DURATION | AFFECTED AREAS | PURPOSE | |
| From | To | |||
| January 14, 2024
(Tuesday) |
8:00 AM | 9:00 AM | > Part of Linasin (near Substation)
> Whole Area of San Isidro > Parts of Consuelo Sur (along Hi-way) > Parts of San Guillermo > Parts of La Paz > Parts of San Isidro
|
Momentary shutdown to facilitate load shifting
|
| 8:00 AM | 06:00 PM | > Whole Area of Linusungan
> Whole Area of Angeles > Whole Area of San Esteban > Parts of Sto Domingo > Parts of Buenavista (Boundary to Linusungan) > Part of Nagbunga > Parts of San Isidro
|
To facilitate replacement of primary lines and clearing of critical vegetation. | |
| 05:00 PM | 06:00 PM | > Part of Linasin (near Substation)
> Whole Area of San Isidro > Parts of Consuelo Sur (along Hi-way) > Parts of San Guillermo > Parts of La Paz > Parts of San Isidro
|
Normalization of loads | |
« Previous 1 … 35 36 37 38 39 … 42 Next »
