Power Interruption

NOTICE OF NGCP SCHEDULED POWER INTERRUPTION

June 11, 2025

 

NOTICE OF NATIONAL GRID CORPORATION OF THE PHILIPPINES (NGCP) SCHEDULED POWER INTERRUPTION


ZAMECO II – Calapacuan, RGS Ice Plant, Castillejos, SanMarcelino,

NETDC San Antonio, San Narciso, San Felipe S/S

ZAMECO I – Taugtog S/S

Consort Land Inc.

Dear Valued Customers:

Please be Informed that we are scheduling power service interruption to your area/power system, details are as follows.

Date/Day Time

Line/Equipment to be De-energized

Activities

June 11, 2025

Wednesday

0530H-0630H

Affected loads:

·      ZAMECO II -Calapacuan, RGS Ice Plant, Castillejos, San Marcelino, NETDC San Antonio, San Narciso, San Felipe

·      ZAMECO I – Taugtog

·      Consort Land Inc.

 

 

Botolan-Castillejos 69 kV Line and Olongapo Cawag 69 kV Lfne

 

Momentary outage for shifting and isolation of loads.

Replacement of insulators at the isolated segment.

Isolation of NETDC San Antonio Line Segment.

·    Consort Land Inc. and RGS Ice Plant        connected to Botolan S/S

·      Calapacuan S/S connected to Olongapo S/S

June 11, 2025

Wednesday 1800H-1900H

Affected loads:

·      ZAMECO II – Calapacuan, RGS Ice Plant, Castillejos, San Marcelino, NETDC San Antonio, San Narciso, San Felipe

·      ZAMECO I – Taugtog

·    Consort Land Inc.

 

 

 

Botolan-Castillejos 69 kV Line and Olongapo-Cawag 69 kV Line

Momentary outage for shifting and isolation of loads (Normalization).

 

·      Taugtog S/S connected to Botolan S/S

·      San Felipe S/S connected to Olongapo S/S

·      NETDC San Antonio line

segment isolated

“In case you or your customers will operate standby generator set during the shutdown, please make sure to trip-off/open your respective breaker/isolator going to our line to ensure safety of our maintenance personnel.”


May 30, 2025

Date TIME DURATION AFFECTED AREAS PURPOSE
From To
May 30, 2025

(Friday)

09:00 AM 04:00 PM > Part of Purok 3 Sindol San Felipe (Purok 3 Arc going to Sitio Tektek & Linasin) > To facilitate installation of new primary pole and re-sag primary line.

> To facilitate relocation of primary poles.

> Clearing of lines.

 


May 29, 2025

Date TIME DURATION AFFECTED AREAS PURPOSE
From To
May 29, 2025

(Thursday)

09:00 AM 04:30 PM > Whole area of San Nicolas, San Miguel, Pundakit, San Antonio

 

> To facilitate installation of capacitor bank.

> To facilitate balancing of loads.

> Clearing of lines.

  09:00 AM 10:00 AM > Whole area of Burgos, San Juan, Rizal, Luna, San Gregorio, Santiago, Antipolo, East Dirita, West Dirita, San Antonio

> Whole area of Beddeng, San Narciso

> Part of Linasin, San Marcelino

> To facilitate load shifting

 

  04:00 PM 04:30 PM > Whole area of Burgos, San Juan, Rizal, Luna, San Gregorio, Santiago, Antipolo, East Dirita, West Dirita, San Antonio

> Whole area of Beddeng, San Narciso

> Momentary shutdown to facilitate normalization of loads.

 