You can purchase high-quality replica watches featuring Swiss-accuracy timekeeping mechanisms and classic styling for under $200, just buy it at https://www.replicaimitation.com.

September 7, 2025

Power Interruption

February 20, 2025

Date TIME DURATION AFFECTED AREAS PURPOSE
From To
February 20, 2025

(Thursday)

09:00 AM

 

02:00 PM

 

> Whole Town of San Felipe (except Maloma)

> Brgy Paite and Omaya of San Narciso

 

> To facilitate installation of recloser along San Felipe Nat’l Road.

> Clearing of lines along backbone.

 

 


February 19, 2025

Date TIME DURATION AFFECTED AREAS PURPOSE
From To
February 19, 2025

(Wednesday)

08:30 AM

04:30 PM

09:30 AM

05:30 PM

 

> Whole Area of San Narciso (except Paite, Omaya, Namatacan, Dalipawen, Beddeng and Parts of Simminublan)

 

> Momentary shutdown to facilitate isolation and normalization of loads.

 

 

 

 

 

08:30 AM 05:30 PM > Whole of Brgy. La Paz, San Rafael, Libertad, Alusiis, Parts of San Pascual, Parts of Natividad (Surgui) San Narciso. > To facilitate installation of recloser along La Paz Road San Narciso.

 

> To facilitate relocation of 3phase primary lines along Alusiis Nat’l Hiway San Narciso.

 

> To facilitate replacement of rotten primary pole along Alusiis Nat’l Road Purok 1.

 

> To facilitate replacement of 2 rotten primary poles at San Pascual (Bernabe Street corner Farrales Street).

 

> Clearing of lines.

 


February 06, 2025

Date TIME DURATION AFFECTED AREAS PURPOSE
From To
February 06, 2025
(Thursday)
8:00 AM

 

 

 

 

5:30 PM

 

 

 

 

> Parts of Calapandayan Subic to Calapacuan Bridge (Whole of Maligaya Village, Subic Beach and private resorts along Calapandayan Nat’l Hi-way)

 

 

> To facilitate replacement of Primary line near Maligaya Village and clearing of lines.

 

 

 

   8:00AM

5:00 PM

8:30 AM

5:30 PM

> Part of Calapacuan

> Whole of Calapandayan

> Whole of Ilwas

> Whole of Baraca Camachile

> Whole of Wawandue

> Whole of Asinan Poblacion

> Whole of Manganvaca

> Whole of Asinan Proper

> Whole of Cawag

> Whole of Pamatawan

> Whole of Aningway Sacatihan

> Momentary shutdown to facilitate load shifting and normalization.
   8:00 AM

5:00 PM

8:30 AM

5:30 PM

>Part of San Roque and San Nicolas, Castillejos

>Whole area of Del Pilar, Castillejos

> Momentary shutdown to facilitate load shifting and normalization.

 


1 20 21 22 23 24 31