January 23, 2025
Date | TIME DURATION | AFFECTED AREAS | PURPOSE | |
From | To | |||
January 23, 2025 (Thursday) |
8:30 AM
|
5:30 PM
|
> Part of Calapacuan Subic Natl Hi-way (Maligaya Village to Studio 23 Salon)
|
> To facilitate replacement of Primary line near Subic Beach.
|
8:30 AM
4:30 PM |
9:00 AM
5:30 PM |
> Part of Calapacuan
> Whole of Calapandayan > Whole of Ilwas > Whole of Baraca Camachile > Whole of Wawandue > Whole of Asinan Poblacion > Whole of Manganvaca > Whole of Asinan Proper > Whole of Cawag > Whole of Pamatawan > Whole of Aningway Sacatihan
|
> Momentary shutdown to facilitate load shifting and normalization. | |
8:30 AM
4:30 PM |
9:00 AM
5:30 PM |
>Part of San Roque and San Nicolas, Castillejos
>Whole area of Del Pilar, Castillejos |
> Momentary shutdown to facilitate load shifting and normalization. |
January 22, 2025
Date | TIME DURATION | AFFECTED AREAS | PURPOSE | |
From | To | |||
January 22, 2025
(Wednesday) |
8:00 AM | 9:00 AM | > Part of Linasin (near Substation)
> Whole Area of San Isidro > Parts of Consuelo Sur (along Hi-way) > Parts of San Guillermo > Parts of La Paz > Parts of San Isidro
|
Momentary shutdown to facilitate load shifting.
|
8:00 AM | 05:30 PM | > Whole Area of Linusungan
> Whole Area of Angeles > Whole Area of San Esteban > Parts of Sto Domingo > Parts of Buenavista (Boundary to Linusungan) > Whole of Nagbunga > Parts of San Isidro > Parts of San Guillermo
|
To facilitate replacement of primary lines and clearing of critical vegetation. | |
05:00 PM | 05:30 PM | > Part of Linasin (near Substation)
> Whole Area of San Isidro > Parts of Consuelo Sur (along Hi-way) > Parts of San Guillermo > Parts of La Paz > Parts of San Isidro
|
Normalization of loads |
January 21, 2025
Date | TIME DURATION | AFFECTED AREAS | PURPOSE | |
From | To | |||
January 21, 2025 (Tuesday) |
8:00 AM | 5:30 PM | > Parts of Nagbunga Castillejos
> Whole of Buenavista Castillejos (except boundary to Linusungan) > Whole of Balaybay Castillejos |
To facilitate replacement of power metering of Castillejos Substation, primary line replacement, relocation of pole and balancing of loads. |
8:00 AM
|
12:00 PM
|
> Whole of Magsaysay
> Whole of Sta Maria > Whole of San Agustin > Whole of San Jose > Whole of San Juan > Whole of San Nicolas > Whole of Del Pilar > Whole of San Roque > Whole of San Pablo > Part of Pamatawan (riverside 1DT only) > Whole of Looc > Whole of Nagbayan > Parts of Nagbunga |
To facilitate replacement of power metering of Castillejos Substation, primary line replacement, relocation of pole and balancing of loads. | |
05:00 PM | 5:30 PM | > Whole of Magsaysay (except Govic Road)
> Whole of Sta Maria (except Sibul) > Whole of San Agustin (except Sibul, Old San Agustin and Madamguiz) > Whole of San Jose (except street from Jireh Home to day care and Uguit) > Whole of San Juan > Whole of San Nicolas > Whole of Del Pilar (except Caballucan) > Whole of San Roque (except Govic Rd) > Whole of San Pablo (except San isidro, Kanaynayan, Bagong Silang and near Govic Road > Part of Pamatawan (riverside 1DT only)
|
> Momentary shutdown to facilitate normalization. |