April 15, 2025
Date | TIME DURATION | AFFECTED AREAS | PURPOSE | |
From | To | |||
April 15, 2025
(Tuesday) |
07:00 AM
|
07:30 AM
|
> Whole Area of Nagbunga
> Whole Area of San Isidro > Whole Area of Linusungan > Parts of Lapaz > Parts of Linasin (near Substation) > Parts of Consuelo Sur (Along Hi-way) > Whole Area of Angeles San Antonio > Whole Area of San Esteban San Antonio > Parts of Buenavista Castillejos (Boundary to Linusungan) |
> Momentary shutdown to facilitate isolation and normalization of loads.
|
07:00 AM | 09:00 AM | > Jollibee San Marcelino | > To facilitate installation of fuse cut-out assembly. | |
07:00 AM | 12:00 MN | > Whole Area of San Guillermo (except Sto. Domingo)
> San Marcelino Pumping Station > Parts of Lapaz SM > Nagbaldian Laoag SM
|
> To facilitate installation of additional distribution transformer for sectionalizing.
|
March 27, 2025
Date | TIME DURATION | AFFECTED AREAS | PURPOSE | |
From | To | |||
March 27, 2025
(Thursday) |
09:00 AM | 05:00 PM | > Part of Sto Nino & San Rafael of San Felipe (San Rafael Elementary school, Brgy San Rafael) Multipurpose Hall)
|
> To facilitate replacement and relocation of rotten primary pole.
> Clearing of critical vegetation.
|
March 26, 2025
Date | TIME DURATION | AFFECTED AREAS | PURPOSE | |
From | To | |||
March 26, 2025
(Wednesday) |
08:00 AM | 12:00 NN | > Uno Farm located at Maowao San Pablo Castillejos
|
> To facilitate relocation of primary pole encroached in private property. |