Date | TIME DURATION | AFFECTED AREAS | PURPOSE | |
From | To | |||
February 06, 2025 (Thursday) |
8:00 AM
|
5:30 PM
|
> Parts of Calapandayan Subic to Calapacuan Bridge (Whole of Maligaya Village, Subic Beach and private resorts along Calapandayan Nat’l Hi-way)
|
> To facilitate replacement of Primary line near Maligaya Village and clearing of lines.
|
8:00AM
5:00 PM |
8:30 AM
5:30 PM |
> Part of Calapacuan
> Whole of Calapandayan > Whole of Ilwas > Whole of Baraca Camachile > Whole of Wawandue > Whole of Asinan Poblacion > Whole of Manganvaca > Whole of Asinan Proper > Whole of Cawag > Whole of Pamatawan > Whole of Aningway Sacatihan |
> Momentary shutdown to facilitate load shifting and normalization. | |
8:00 AM
5:00 PM |
8:30 AM
5:30 PM |
>Part of San Roque and San Nicolas, Castillejos
>Whole area of Del Pilar, Castillejos |
> Momentary shutdown to facilitate load shifting and normalization. |