Date | TIME DURATION | AFFECTED AREAS | PURPOSE | |
From | To | |||
January 22, 2025
(Wednesday) |
8:00 AM | 9:00 AM | > Part of Linasin (near Substation)
> Whole Area of San Isidro > Parts of Consuelo Sur (along Hi-way) > Parts of San Guillermo > Parts of La Paz > Parts of San Isidro
|
Momentary shutdown to facilitate load shifting.
|
8:00 AM | 05:30 PM | > Whole Area of Linusungan
> Whole Area of Angeles > Whole Area of San Esteban > Parts of Sto Domingo > Parts of Buenavista (Boundary to Linusungan) > Whole of Nagbunga > Parts of San Isidro > Parts of San Guillermo
|
To facilitate replacement of primary lines and clearing of critical vegetation. | |
05:00 PM | 05:30 PM | > Part of Linasin (near Substation)
> Whole Area of San Isidro > Parts of Consuelo Sur (along Hi-way) > Parts of San Guillermo > Parts of La Paz > Parts of San Isidro
|
Normalization of loads |