Date TIME DURATION AFFECTED AREAS PURPOSE
From To
January 22, 2025

(Wednesday)

8:00 AM 9:00 AM > Part of Linasin (near Substation)

> Whole Area of San Isidro

> Parts of Consuelo Sur (along Hi-way)

> Parts of San Guillermo

> Parts of La Paz

> Parts of San Isidro

 

Momentary shutdown to facilitate load shifting.

 

 

 

 

 

  8:00 AM 05:30 PM > Whole Area of Linusungan

> Whole Area of Angeles

> Whole Area of San Esteban

> Parts of Sto Domingo

> Parts of Buenavista (Boundary to Linusungan)

> Whole of Nagbunga

> Parts of San Isidro

> Parts of San Guillermo

 

To facilitate replacement of primary lines and clearing of critical vegetation.
  05:00 PM 05:30 PM > Part of Linasin (near Substation)

> Whole Area of San Isidro

> Parts of Consuelo Sur (along Hi-way)

> Parts of San Guillermo

> Parts of La Paz

> Parts of San Isidro

 

Normalization of loads