Date TIME DURATION AFFECTED AREAS PURPOSE
From To
November 27, 2024

(Wednesday)

8:00 AM 9:00 AM > Part of Linasin  (near Substation)

> Whole Area of San Isidro

> Parts of Consuelo Sur (along Hi-way)

> Whole Area of San Guillermo

> Whole Area of La Paz

> Parts of Nagbunga, San Marcelino

(WLAC Road)

 

> Parts of Nagbunga, Castillejos

 

> Momentary shutdown to facilitate load shifting.

 

 

 

 

 

  8:00 AM 06:00 PM > Whole of Sto Domingo

> Whole Area of Linusungan

> Whole Area of Angeles

> Whole Area of San Esteban

> Parts of Buenavista (Boundary to Linusungan)

> Part of Nagbunga, San Marcelino

 

> To facilitate paralleling of three phase line.

> To facilitate removal of old pole in front of SAVEMORE San Marcelino.

> To facilitate replacement of rotten primary poles at Angeles.

 

  05:00 PM 06:00 PM > Part of Linasin  (near Substation)

> Whole Area of San Isidro

> Parts of Consuelo Sur (along Hi-way)

> Whole Area of San Guillermo

> Whole Area of La Paz

> Parts of Nagbunga, San Marcelino

(WLAC Road)

 

> Parts of Nagbunga, Castillejos

 

> Normalization of loads.