Date TIME DURATION AFFECTED AREAS PURPOSE
From To
September 17, 2026

(Thursday)

08:30 AM

 

09:30 AM

 

>Whole of Magsaysay (except Govic Road)

>Whole of Sta Maria (except Sibul)

>Whole of San Agustin (except Sibul, Old San Agustin and Madamguiz)

>Whole of San Jose (except street from Jireh Home to day care and Uguit)

>Whole of Del Pilar(except Caballucan)

>Whole of San Roque(except Govic Road)

>Whole of San Pablo (except San isidro, Kanaynayan, Bagong Silang and near Govic Road

> Part of Pamatawan (riverside 1DT only)

 

>To facilitate isolation of loads.

 

  08:30 AM

 

12:00 NN >Whole of San Nicolas and Balaybay Castillejos >To facilitate energization of recloser along Baring San Nicolas.
  08:30 AM

 

04:30 PM > Part of San Juan Castillejos (Municipal Hall of Castillejos, St. Nicholas Academy, St. Nicholas Parish, Aldersgate, Central Elementary School, Brgy San Juan Plaza, Public Market)

 

>To facilitate conversion of 1phase primary line to 3phase primary line.