Date TIME DURATION AFFECTED AREAS PURPOSE
From To
March 19, 2026

(Thursday)

06:00 AM 06:00 PM > Parts of San Pascual, Libertad, San Juan, Patrocenio including PMMA San Narciso

> Whole of La Paz & Grullo San Narciso

>To facilitate the Paralleling of Three Phase Backbone Line along San Narciso.

 

  06:00 AM 08:00 AM > Whole of Beddeng San Narciso

> Whole of San Antonio except part of Linuron

>To facilitate tapping of new backbone lines along San Narciso.

 

  06:00 AM

05:00 PM

07:00 AM

06:00 PM

> Whole of San Narciso

>Parts of Manglicmot, East Feria, Apostol, Sto Niño, Sitio Arros San Felipe

 

> To facilitate load shifting and normalization of loads.