| Date | TIME DURATION | AFFECTED AREAS | PURPOSE | |
| From | To | |||
| January 18, 2026
(Sunday) |
06:00 AM
01:00 PM |
06:30 AM
01:30 PM |
> Part of Magsaysay (Govic Rd)
> Parts of Nagbunga (Hanjin Village) > Parts of San Pablo (San Isidro, Kanaynayan, Bagong Silang and near Govic Rd) > Parts of San Roque (near Govic Rd) > Parts of Del Pilar (Caballucan) |
>Momentary shutdown to facilitate isolation and normalization of loads.
|
| 06:00 AM
|
01:30 PM
|
>Whole of Looc and Nagbayan Castillejos
>Part of Magsaysay Castillejos (Cemetery Road) > Parts of San Agustin (Sibul, Old San Agustin and Madamguiz) > Parts of Sta. Maria (Sibul)
|
>NGCP requested shutdown to facilitate the replacement of 230kV line overhead ground wires. | |